No Race to Judgment on Bond Claims

On May 24, 2010, Division I of the Washington Court of Appeals held that where two claimants against a specialty contractor's bond have the same statutory priority, the first of the claimants does not gain priority by being the first to reduce the claim to judgment.  The case, Hosea v. Toth, can be viewed here:  Download file

Continue Reading...
Tags:

Brightwater Lawsuit

On Monday, April 19, King County filed a $74 million default termination suit against one of its Brightwater contractors and its surety. A copy of the complaint is available here.  Download file

Tags:

One Policy Limit or More? Division 1 Interprets Anti-Stacking Clause

Here is Division 1's most recent analysis on the arcane but important issue of how many policy limits are available in a situation where a carrier issues multiple year-to-year CGL policies and the insured becomes legally obligated to pay for damage that occurs over those multiple year but results from the same continuous or repeated cause (i.e., water seepage). 

The answer, at least in this case with this policy language was:  1 policy limit, under the clause known as the anti-stacking provision.

Copy of opinion also available here Download file

Condo Defect Claim Dismissed on Causation Grounds

A fitting way to end the week...the latest dispatch from the Great Condo Wars:  Division 1's recent opinion in Ballard Residential v. Pacific Rim Framing establishes:

  • Defect Causation:  The condo used prefabricated Tyvek panels for the exterior.  Pacific Rim did not install the Tyvek, but did list in its scope of work the obligation to "staple and tape ends of panelizer installed Tyvek vapor barrier."  Eventually, the Tyvek panels fell off and/or permitted water intrusion.  The Association sued Pacific Rim (the framer) for its alleged losses; in a decision that renews faith in the ability to get and defend a summary judgment even on a complex record, Division 1 sifted the evidence and concluded there was no breach by Pacific Rim of its limited duty to staple down the Tyvek that actually caused the Association's alleged losses.
  •  Indemnity:  Just as its breach claim against Pacific Rim failed for lack of causation, so too the Association's claim that the framer was required to indemnify for the siding failure fell apart because the claim was not one "arising out of, resulting from or connected with" Pacific Rim's own scope of work.  The Court refused to treat the standard indemnity clause as a type of project-wide insurance.
  • Tender of Defense:  The Court called the Association's notice of tender of defense to Pacific Rim "perfunctory" and suggested that for such a tender to be valid, the tender must be accompanied by a bill of particulars actually establishing the fact of the indemnitor's ultimate liability...but since this is an unpublished decision, take that with a grain of salt.

Copy of opinion also available here Download file

Division 1 Restores Lien, Limits Application of "Summary" Procedure to Dismiss Frivolous Liens

Division 1 in this new case raises the bar a bit higher on RCW 60.04.081's summary procedure for vacating frivolous liens on private jobs -- the lien must be "so devoid of merit that the claim has no possibility of succeeding."

The Court offered three examples for when the summary process (decided on motion with no live testimony) is best suited -- whether the lien is signed by the proper party, whether the lien was properly served, and whether the lien's content complied with statutory requirements.  The case in question, by contrast, involved issues of scope of work and intent of the underlying subcontract.

Copy of opinion also available here Download file

Tags: ,

Division 1 Clarifies Estoppel Remedy for Bad Faith

This case, the latest from Division 1 in its treasure chest of condo defect / insurance coverage cases, contains two notable nuggets:

  1. A 14 month delay in responding to a tender of defense and indemnity was bad faith as a matter of law, estopping the carrier from denying coverage under the additional insured endorsement it issued to a GC under a subcontractor's policy.  As a result, the carrier had to pay both the defense costs incurred by the GC as they pertained to the subcontractor's scope of work as well as the portion of a related settlement that the GC paid to the HOA.
  2. That estoppel remedy, however, did not run so far as to sweep into the policy liability for claims made against the GC that arose from work not performed by the particular subcontractor that the carrier insured.  The Court rejected the GC's argument that bad faith in handling a claim related to a particular sub's work made the carrier liable for all of the GC's liabilities on the entire project, regardless of cause. 

Copy of opinion also available here Download file

No "Property Damage" Trigger for Tank Leakage

Walla Walla College hired a tank company in 1991 to install two underground gas storage tanks.  In 2001, approximately 10,000 gallons of gas leaked from one tank into the ground.  The tank installation contractor had two CGL policies in effect from 1990 to 1992. 

Seeking coverage under those policies to pay for the cleanup costs, the College claimed that the triggering "property damage" occurred at the time of installation in 1991 due to the installer's failure to use proper backfill which in turn set in motion stress to the tank which ultimately lead to the failure and leakage.  The carrier, on the other hand, claimed that there was no covered "property damage" until the leakage in 2001.

Division Three held that mere stress to the tank was not enough to constitute "property damage" and therefore denied coverage for the loss under the 1990-1992 policies.  First, the Court noted that the "your product" exclusion" negated any coverage for loss in value to the tank itself.  Next, the Court distinguished continuous trigger cases such as Groul Construction Co., Inc. v. Ins. Co. of North America, 11 Wn.App 632 (1974) by noting that while "a process began" in 1991, the "property damage did not occur until the tank failed in September 2001, long after the policies had expired."

9th Circuit Certifies Economic Loss Doctrine Issues to Washington Supreme Court

A classic economic loss scenario: 

The City of Seattle owns the Monorail between downtown and Seattle Center and has a contract with a JV who operates the Monorail.  In 1999, the City hired a design firm (LTK) under a separate contract to identify and repair problems with the Monorail trains.  The JV had no contractual relationship with LTK.  In 2004, one train caught fire.  The JV's insurance company paid the claim then blamed LTK for causing the fire. 

Got it? 

Into the thicket of Washington's economic loss doctrine now comes the 9th Circuit in this recent case certifying a question of state law to the Supreme Court, specifically:

May party A (here, SMS, whose rights are asserted in subrogation by [carrier]), who has a contractual right to operate commercially and extensively on property owned by non-party B (here, the City of Seattle), sue party C (here, LTK) in tort for damage to that property, when A (SMS) and C (LTK) are not in privity of contract?

At first blush, this issue might appeared to have been cleanly resolved by Berschauer/Philips v, Seattle School District (1994), but wait: the 9th Circuit thinks there are unresolved issues lurking in that case that need to be addressed: 

  1. First, the 9th Circuit notes that in Berschauer the claimant had been assigned the right to prosecute claims against the remote third party and thus the claimant still had a meaningful remedy.  Would the doctrine still apply in this situation, where the JV appears not to have acquired the right to sue LTK by way of assignment of rights from Seattle?
  2. Second, is the JV's right to operate the Monorail a "property right" such that fire damage to the train would come within an exception to the doctrine for harm to personal injury or property damage?

Stay tuned...the Supreme Court is not bound by the 9th Circuit's framing of the issue and could use this case as an opportunity to significantly revise the scope of the economic loss doctrine in Washington.

 

Statutes of Limitation Not Applicable to Safeco Field Defect Claims

In a case of first impression, the Supreme Court yesterday held that because the primary purpose of Safeco Field is public recreation, claims stemming from design and construction of the stadium are exempt from the statute of limitation under RCW 4.16.160 (which provides that claims brought for the benefit of the state are not subject to statutes of limitation).  This is believed to be the first case in the country addressing the time periods for suit applicable to professional sport facilities constructed with public and private funds.

The decision clears the way for the two plaintiffs (the PFD and the Mariners) to collect more than $3 million in damages from the contractor JV based on the failure of the intumescent fire protection coating system on the stadium's structural steel.

Copy of opinion also available here Download file

Notice Defense Is Subject to Arbitration, Not "Predicate Requirement" to Enforcement of Arbitration Clause

The contract in this case stated a time limit on claims -- 21 days after occurrence of the event giving rise to the claim (fairly typical AIA clause).   The subcontractor argued that the arbitration clause did not apply because (1) the contractor failed to comply with the 21 day notice rule and (2) the 21 day notice rule was a "condition precedent" to enforcement of the arbitration clause.

Division 1 held that the notice defense is for the arbitrator to decide and was not a condition precedent.  In distinguishing the Mike Johnson case, however, the Court seemed to suggest that the parties are generally free to rewrite the arbitration clause to make the 21 day notice rule a true condition precedent (and thereby preserve the notice issue for judicial -- not arbitral - resolution).

Copy of opinion available here Download file

CPA Claim Is Only Claim to Survive in Harbor Homes Appeal

In this case, 10 homeowners who bought homes from the original purchaser-occupants of a Harbor Homes project in Snohomish County sued the original developer (Harbor) for construction defects.  Each claim (save the Consumer Protection Act claim) was mowed down by Division One as follows:

  1. Implied Warranty of Habitability.  Because this warranty only extends to original purchaser-occupants and may not be assigned to subsequent purchasers, this claim was dismissed.
  2. Intentional Fraud.  The Court held that this claim is barred by the economic loss doctrine.
  3. Assignment of CPA and Contract Claims.  The Court upheld the validity of the assignments of claims made from the original purchasers to the next generation buyers, thereby allowing the subsequent purchasers to bring Consumer Protection Act and contract breach claims that were once owned by the original buyers.
  4. Merits of CPA Claim.  On the merits, the Court held that the homeowners presented sufficient evidence to avoid summary judgment on their CPA claims and that they were entitled to a full trial.
  5. Merits of Good Faith and Fair Dealing Claim.  For their assigned contract claim, the homeowners alleged that Harbor violated the implied duty of good faith that exists in any contract.  They evidently failed to point to any specific contractual term that was violated, however, and on that ground the Court dismissed this claim.

Copy of opinion also available here Download file

Claim Filing Requirement in RCW 4.96 Not Applicable to Construction Contract Dispute

In Matia Contractors v. City of Bellingham, Division 1 held yesterday that RCW 4.96 -- which requires a written claim to be submitted before suit is brought against a city -- does not apply to a contractor's breach of contract action.
Tags:

Settlement Agreements

So you wrap up a lawsuit and enter into a settlement agreement in which one side agrees to pay money to the other side in exchange for mutual releases and other typical settlement clauses.

But then the party required to make the payment, well, doesn't pay.  What happens to the claims that were released?  Do they come back to life?  Or does the failure to pay merely give the wronged party to right to sue to enforce the payment obligation in the settlement agreement?

Division 1 holds in this case that, unless clearly stated otherwise, a settlement agreement is merely an "executory" contract rather than a "substituted" contract -- and therefore the wronged party can revive its released claim and go back to court. 

Copy of decision also available here Download file

More News from the Condo Wars....

This new case from Division 1 arose out of a condo project.  After settling its claims with the developer, the GC sued several subcontractors for breach of contract and indemnity.  All but one of the subs settled with the GC.  The remaining sub went to trial and lost.  On the sub's appeal, the Court of Appeals held:

  1. The GC's breach of contract claim vs. the sub accrued (and thus began to run, for purposes of the 6 year statute of limitation) at the earlier point when the sub itself performed the defective work, not at the later time of substantial completion of the overall project.
  2. On the GC's indemnity claim, the Court of Appeals refused to give the sub an offset based on the settlements the GC had achieved with the other subcontractors, because the sub failed to prove that the other settlements paid the GC for damages caused by its work.
  3. The Court held that the way the trial court apportioned responsibility for the GC's legal fees -- apportioning 1/13 of the total to the sub because there were a total of 13 subs on the project -- was arbitrary and without basis.

Download file

Contract Interpretation Issues Dominate Two New U.S. Court of Federal Claim Cases

In two recent decisions, the U.S. Court of Federal Claims engaged in some heavy duty contract interpretation -- focusing primarily on what constitutes a patent ambiguity in plans which bidders are required to bring to the owner's attention before submitting bids.

In this case, the contractor was disallowed any extra costs because the Court concluded that the specifications were clear.  Just to give you some indication of how closely the Court parsed the language, a key part of the ruling was based on the absence of a comma in a particular sentence (which the Court took to mean that the final clause "as indicated in the drawings" modified only the noun immediately prior to this subordinate clause not the entire sentence).

This case ended more happily for the contractor when the Court ruled that the distortion of the standing seam metal roof (which the contractor was to provide under a performance specification) was actually caused by flaws in the owner-furnished design specification for the building structure. 

Tags:

Division 2: Venue Clause Not Part of Contract in Sales Transaction Between Merchants

Describing UCC Article 2-207 as a "defiant lurking demon" condemning its interpreters to "depths of despair," Division 2 nonetheless wrestled with the demon long enough to conclude that the terms listed in a stream of invoices from a merchant seller to a merchant buyer -- a venue provision, disclaimers of liability, etc -- were not enforceable.  Must read for your next battle of the forms case.

Copy of opinion also available here Download file

Supreme Court Clarifies "Implied Waiver" Exception to Mike Johnson Rule

The City of Olympia has won its Mike Johnson appeal to the Washington Supreme Court.   You can get quick background on the case here and you can read the new opinion here.  Essentially, the Court clamped down on the "implied waiver" exception to the general rule mandating compliance with contractual notice and suit deadlines.

Copy of opinion also available here Download file

Tags:

Severin Watch

This procedurally tangled case between Fluor and the structural steel subcontractor Walter on the DOC project in Aberdeen will be of virtually no interest to anyone but the parties themselves, except for the following two kernels:

  1. The Court of Appeals recognizes -- and presumably adopts in Washington -- the federal Severin doctrine (a GC who has been fully released of liability from its sub cannot pass-through the sub's claim to the owner); and
  2. The Court also applies the old Balfour case (OK, maybe not that old -- decided in 1980) in which the Supreme Court said as a general matter that courts lack the authority to order consolidation of two separate arbitration proceedings.

Copy of opinion also available here Download file

Court Rejects Spearin Claim

The venerable Spearin doctrine receives a thorough vetting in this new Court of Federal Claims case.  In decidedly pro-owner fashion, the Court denied a structural steel fabricator's Spearin claim against the VA.

Copy of opinion also available here Download file

Tags:

Severin!

A rare sighting of the Severin doctrine is on display in this Division 2 case released yesterday in the Natkin-Scott v. M+W Zander litigation.

As Severin encourages, a GC and sub entered into a pass-through agreement whereby the GC assigned its rights against the owner to the sub & the sub agreed to look solely to the owner for recovery in alleged impact claims.

There was one major but unknown problem -- the GC was unregistered & thus lacked the authority to bring claims against the owner.  The assignment of claims was, therefore, hollow.  After the owner defeated the pass-through claim on this ground, the sub turned back against the GC claiming the GC had breached an implied warranty that the assigned cause of action actually existed (relying on Section 333 of the Restatement (Second) of Contracts).

Division 2 held in favor of the GC and dismissed all of the sub's claims.  The basis of the holding was language in the Severin Agreement that both parties assume the risk of any mistake of fact or law.  The Court held that the GC's lack of registration -- and consequent lack of authority to bring claim -- was a mistake shared by both GC and that the risk of that mistake was transferred to the sub under the terms of the Severin Agreement.

Copy of opinion also available here Download file

Tags:

Breach Without Damage? Court Holds Suit May Be Dismissed

With the rise of condo defect cases came the phenomenon of claims based on technical violations of plans or applicable codes without much in the way of resulting damage to the structure.  This case sheds some light on whether a plaintiff can still maintain a breach of contract action for money recovery under these circumstances.  The answer seems to be that a breach by itself is not enough.  Damage must be shown.

The case also has some pearls of wisdom on the following issues:

  1. Who decides -- judge or jury -- the amount of legal fees to be awarded when the fees are sought as an element of "damages" under an indemnity clause rather than under a prevailing party fee clause?  Answer:  the jury.
  2. What are the elements of an enforceable contract where -- as often seems to happen -- the deal arises out of informal communications without final mutual signatures?  Check out the discussion.
  3. Does an indemnity clause covering "any and all claims" cover both tort and contract claims?  Answer: yep.

A copy of the opinion also available here Download file

Contractor Not Liable Under False Claims Act

On April 5, we covered an issue that seems to be gaining momentum -- counterclaims by the public owner under the False Claims Act for damages caused by falsely submitted claims for extra compensation.

This new case from the U.S. Court of Federal Claims is another example of this trend.  The decision contains useful guidance on two key issues -- (1) what constitutes a "false" claim and (2) what conduct by the contractor rises to the level of prosecuting the claim with "reckless disregard" of its falsity.

Copy of decision also available here Download file

Tags:

Government Allowed to Prosecute Fraud Counterclaim

Taking the offensive against a claim it believed to be knowingly false, the USDOT in this case arising from a roadway project in Eastern Washington filed a counterclaim against the contractor under three federal statutes -- the False Claims Act, the the anti-fraud provisions of the Contract Disputes Act and the Forfeiture of Fraudulent Claims Act.

The gist of the fraud claim is that the contractor overbilled for work, such as billing for testing costs which had already been paid & billing for work which should have been included in the base contract.

The contractor moved to dismiss the counterclaim for lack of evidence to establish either that the claim was false or that the contractor submitted the claim with knowing intent to defraud.  The Court of Federal Claims denied the motion, holding the Government had shown enough facts to establish a "reasonable possibility" of success on the fraud counterclaim.

 

 

Tags:

Mike Johnson Bill Withdrawn

Legislation to overturn the Mike Johnson decision, sponsored by the AGC, was officially withdrawn yesterday.  Third time not a charm after all...

Tags:

Next Stop, Senate...

Substantially revamped bill to overturn the Mike Johnson case easily passes in the House and moves on to the Senate.  Summary of recent changes described here.
Tags:

Crane Operator May Have "Seaman" Status under Jones Act

When is a crane operator hired by a GC to run a crane mounted on a derrick barge for a project to rehabilitate a cruise line terminal actually a "seaman" protected by the federal Jones Act? 

Traylor Brothers found out in this 9th Circuit case that the answer is "it depends."  The Court reversed summary judgment for Traylor & remanded for a trial on the merits, holding the crane operator was entitled to have the jury decide the issue.  Under the Jones Act, a "seaman" is permitted to sue in tort for damages and is not limited to recovery of workers comp benefits.

Tags:

Supreme Court Overrules "Completion and Acceptance" Doctrine

The venerable completion & acceptance doctrine -- which holds that a builder is immune from personal injury suit filed by injured third parties once the owner has accepted the completed work -- is now officially dead in Washington, according to this new 6-3 ruling frorm the Supreme Court. 

The facts of the case were that Baugh completed its work on a processing facility in 1997.  In 2000, the owner suspected a leak in one of the pipes installed by Baugh and sent in a crew to excavate the area to find the leak.  A crew member died when the excavation hole collapsed.  The suit by the deceased worker's estate against Baugh was thrown out by the lower court based on the completion & acceptance doctrine.

Reinstating the suit, the Supreme Court adopted the rule that a negligent builder can be sued by an injured third party, subject to the 6 year statute of repose.

 

 

Tags:

Division 1 Rejects "Cumulative Impact" Claim

This dispute between Strand Hunt (SH) and Lake Washington School District arose from a $37 million school renovation project.  SH filed an impact claim of approximately $4.5 million based on alleged delays and "cumulative impacts" to the work.  The trial court granted summary judgment to the owner and Division 1 affirmed, leaving SH with no recovery.

The notable holdings are as follows:

  1. Relying on the Mike Johnson case, Division 1 held SH waived its right to claim for "cumulative impacts" because it failed to submit pricing for such indirect impacts when submitting its pricing for direct cost of the changed work.  The Court rejected SH's argument that it was "impossible" for it have ascertained these indirect costs at the time.  The Court also held that the "event" giving rise to the claim for cumulative impact was the changed work itself, not SH's subsequent "realization" that changes had a cumulative effect.
  2. SH was not allowed to make a claim for quantum meruit as the contract provided a specific mechanism for pricing of changed work.
  3. The contract's terms for pricing of changed work did not violate RCW 4.24.360 (the statute which voids as against public policy any terms which purport to "waive release or extinguish" the right to seek delay costs).
  4. Describing the Eichleay remedy as "severely limited," the Court adopted recent federal case law which makes Eichleay applicable only when a true suspension occurs.

 

Tags:

Supreme Court Rules for Contractor in "Scoccolo" Case

Well, that settles that...or does it?  Today the Supreme Court issued its decision in the long-running dispute dispute between Scoccolo Construction and the City of Renton - a complete victory for the contractor.  Justice Madsen's concurring opinion, however, raises legitimate questions on just how precedential today's decision is.

This site previewed the Scoccolo case back in May.  The basic issue in the case is the meaning of the acting for" clause in the RCW 4.24.360, which makes it void against public policy for a construction contract to purport to waive the right of the contractor to sue for damages for delay caused by the contractee/owner or persons "acting for" the contractor/owner.

Scoccolo claimed its road widening project was impacted by the failure of certain utilities (Puget Power, US West, TCI Cable) to relocate their utilities to facilitate the progress of the work within Scoccolo's contract.  The trial court ruled as a matter of law the utilities did "act for" the City and, on the basis of that ruling, the jury awarded roughly $400,000 in damages.

The Supreme Court upheld the damage award, finding that the City's power to compel the utilities to relocate their utilities under franchise agreement meant the utilities "act for" the City for purposes of the delay statute.  Unfortunately, the Court does not appear to have separately decided the statutory meaning of the "acting for" clause apart of the way it was interpreted in the jury instruction in this case (which was not challenged on appeal), and for that reason the book may not be fully written on this issue as noted in Justice Madsen's concurrence.

Tags:

Mitigation Defense Based on Force Majeure Clause For Jury to Decide, Not Court

A subcontractor was operating a crane when it rolled over and damaged two conveyor belts being used to transport coal at the Centralia energy plant.  This in turn caused a plant shutdown, which caused the customer to purchase energy on the open market to fulfill its requirements to third parties during the shutdown.  This case involved the customer's suit against the subcontractor to recover the extra energy costs.

The trial court had entered summary judgment in favor of the subcontractor, based on its argument that the customer failed to mitigate its damages.  The subcontractor's mitigation theory was that the customer need not have purchased energy on the open market to fill current requirements to third parties because its obligations to those third parties were discharged by a Force Majeure Clause that allowed the customer to suspend its performance if its inability to perform was due to factors outside its control.

Reversing on appeal, Division 2 held that the effect of the Force Majeure Clause on the customer's duty to mitigate was a question of fact for the jury - specifically, whether the customer acted "reasonably" by not invoking the Force Majeure Clause to suspend energy deliveries to third parties.

 

Tags:

Contractor Allowed to Proceed on DSC and Specifications Theories in Roadway Dispute

Where is the line of distinction between a defective specifications claim and a differing site conditions (DSC) claim?  For an example of why this matters, check out this new decision from the Court of Federal Claims arising out of a Washington road improvement project.

The contractor complained that the aggregate specified for use in the design documetnts for re-surfacing the road was unsuitable.  In its complaint, the contractor alleged various theories, among them defective specifications and DSC.   The government moved for summary judgment on the grounds that the DSC and specifications claims were redundant.  The Court denied the motion, allowing the contractor to proceed on both theories.
Tags:

Division 2: Jury to Decide Whether Owner Waived Contract's Suit Limitation Period

In this latest installation in the Mike Johnson saga, Division 2 held this week that the City of Olympia must go to trial on a contractor's $768,000 impact claim arising out of a sewer line project.

The case was before Division 2 on the contractor's appeal from a grant of summary judgment in favor of the City.  The contract was governed by the WSDOT Standard Specifications, which in Section 1-09.11(3) provide that any suit must be filed within 180 days of final acceptance.  Because the suit was not brought within that time, the City moved for summary judgment and prevailed.

On appeal, Division 2 concluded that a triable issue of fact existed on whether the City had waived enforcement of the 180 day suit limitation when it engaged in claim negotiations with the contractor after expiration of the applicable suit period.  The Court distinguished Mike Johnson as a case where the owner  (who also engaged in claim negotiations) had "continuously asserted" that it did not intend any waiver of defense during the negotiations. 
Tags:

SJ Denied in Idaho DSC Claim

Like a lot of differing site conditions (DSC) cases, this new case only makes sense if you spend the time to read the whole decision and absorb the details concerning what the contract "indicated" the builder would encounter. When all is said and done, Universal Construction, Inc. dodged the summary judgment bullet in a claim arising from a $500,000 road project in Idaho.

Tags:

Supreme Court Approves "Stigma" Damages in Defect Case

At the end of its recent decision involving discovery sanctions against the maker of an EIFS product, the Supreme Court announced a significant damages ruling: in a defect case, where the damage to property is "permanent" in nature, the plaintiff will be entitled to both the cost of repair and dimunition in property value. Said the Court by a 9-0 vote:

(5) Damages for Diminished Value. Sto argued that the trial court erred in awarding the Mayers "stigma damages," damages for the home's diminished value. However, where the damage to real property is permanent, a plaintiff is entitled to recover, not only for the costs of restoration and repair, but also for the property's diminished value. See Pugel v. Monheimer, 83 Wn. App. 688, 692, 922 P.2d 1377 (1996) (determining that withdrawal of building's lateral support permanently damaged marketability); see also Grant v. Leith, 67 Wn.2d 234, 237, 407 P.2d 157 (1965) (sustaining an award for restoration and permanent depreciation). The Court of Appeals noted that "{t}he Mayers presented unrebutted expert testimony that in addition to the repairs, they had suffered a permanent loss because they will have to disclose that the home is sided with EIFS, a known defective product." 123 Wn. App. at 464. We affirm the Court of Appeals on the trial court's award of stigma damages.

Tags:

Supreme Court Interprets Prelitigation Notice Rules in RCW 64.50

The first in this term's Supreme Court roster of cases pertinent to the construction industry is out: the Lakemont Ridge case. By a 9-0 vote, the Supreme Court held that a homeowner need not file its 45 day pre-suit notice to cure in a situation where the "construction professional" has failed to file its own notice advising the homeowner of the existence of the homeowner's pre-suit notice requirement. The takeaway quote:

The statute unambiguously establishes two distinct notice requirements. These provisions of chapter 64.50 RCW operate together to achieve the legislature's dual goals of reducing potentially burdensome and expensive construction defect litigation and preserving rights and remedies for property owners. We construe the statute to give effect to both notice provisions. At the beginning of the parties' relationship, the construction professional must notify the homeowner of the construction professional's right to notice and the opportunity to cure any defects. RCW 64.50.050(1). If the construction professional fails to provide the notice required by this section, the Act ensures that the homeowner's failure to give prelitigation notice "shall not preclude or bar any action." RCW 64.50.050(3). However, if the construction professional
provides notice of the prelitigation notice requirement, the homeowner must give prelitigation notice of the alleged defects and follow the statutory procedures designed to avoid litigation. RCW 64.50.020(1). This interpretation gives effect to each notice provision of chapter 64.50 RCW.

Tags:

Sewer Claim Flushed by Division 3

A backed-up city sewer system overflowed into a home and caused floor damage, among other things. The occupants sued the city for negligence, claiming $15,900 in repair and cleanup expenses. Division 3 affirmed summary judgment in favor of the City.

The Court rejected the theory the City was strictly liable without proof of actual fault -- and likewise rejected the res ipsa loquitur claim. In a nutshell, plaintiff in this context cannot prevail on the theory that the City maintains exclusive control over the sewer system and is thereby guilty for whatever happens.

Tags:

Ambiguous Specification Claim Fails for Lack of Reliance Evidence

This new ASBCA case stemming from a Bremerton project is pretty dense to read (so what's new about ASBCA decisions?), but it contains a valuable legal nugget toward the end: merely proving that a bid specification is ambiguous is not enough to obtain compensation from the government - the claimant must in addition demonstrate "reliance" on the poor specification (i.e., that the bidder in fact based its bid price on its interpretation of the ambiguous specification). Otherwise, the claim is rejected as in this case.

Tags:

How Far Does Spearin Go?

The U.S. Supreme Court's decision in the 1918 case of Spearin v. U.S. remains one of the landmark construction law cases. In rough terms, it stands for the rule that an owner, by sponsoring a set of plans, makes an implied warranty to the builder that the plans are adequate for their intended purpose.

The exact reach of Spearin in a particular case is the subject of 100s of cases across the country. One of the latest and most interesting is this Ohio opinion which finds in favor of the owner and denies the builder's monetary claim for impacts and delays allegedly attributable to bad plans.
Download file

Continue Reading...
Tags:

LD Clause Precludes Separate Recovery of Lost Profits

The accepted wisdom is that a liquidated damage clause in a construction agreement is the exclusive remedy for time-related damages. Here's a new case that seems to follow the accepted wisdom and perhaps go a bit beyond, holding the LD clause to preclude any type of additional "actual damages."

Given the preclusive effect of LD clauses, sometimes an effort is made to carve out exceptions or to make the clause alternative at the option of the owner -- that is, to permit the owner to collect either the LD amount or actual damages, whichever is greater. But the "optional" may not be enforceable if this case were to be adopted in Washington.

Tags:

Owner Not Liable for Injury to Employee of Independent Contractor

While there is nothing especially groundbreaking about this new case, it does illustrate the legal grounds why owners most often avoid liability for injuries sustained by workers hired by independent contractors doing work on the construction site.

Tags:

9th Circuit: Reasonable Use Doctrine Shields Owner from Claims Based on Dewatering Activity

Abbott Labs wanted to build a new basement for its manufacturing facility. To do so, it had to pump out a lot of groundwater. But this pumping depleted groundwater in neighboring property as well, where pecan farmers had maintained trees whose roots depended on a water level of about 16 feet. After the pumping, the water table was permanently suppressed to 32 feet. The trees died.

Relying in significant part on a 1935 Washington case, the Ninth Circuit recently held that the owner owed no duty of care to neighboring landowners.

Continue Reading...
Tags:

The "Completion and Acceptance" Doctrine in Washington

It's rare for a construction case to reach the Supreme Court, and rarer still when the issue presented is the infrequently explored "completion and acceptance" doctrine.

On November 9, 2005, the Supreme Court will hear argument on the validity of "completion and acceptance" doctrine, which generally provides that a contractor's liability to third parties is extinguished when the contractor's work is complete and accepted by the owner. The case is
Davis v. Baugh Indus. Contractors, Inc.

Continue Reading...
Tags:

Overcoming the "Economic Waste" Doctrine

The "economic waste" doctrine is an equitable doctrine that must give way to whatever remedy is provided for in the contract between the parties. So sayeth Division I in a recent case involving a Costco store in Bellingham.

Tags:

Owner Beware: No "Third Party Beneficiary" Status

A recent case out of Division II highlights the rather precarious position occupied by the Owner in a turnkey project delivery -- whether commercial or residential: you can't sue remote contractors or trades because you are generally not considered to be a "third party beneficiary" of your seller's contracts with the firms that actually built your home or facility. That leaves the Owner's remedies limited to whatever the purchase and sale agreement may provide, not what the underlying construction contracts may provide.

Continue Reading...
Tags: